MLT Engineering / Technical article / TAML-3 Lite

Brownfield well architecture · TAML-3 Lite

Brownfield Sidetracking and the Value of the Parent Bore

When the existing bore still produces, a sidetrack decision should compare the value of the new target with the reservoir value that may be surrendered by abandoning the parent production path.

Parent retainedExisting production path can remain part of the development architecture.
Temporary isolationProtect the parent bore during casing-exit and lateral construction.
One-trip casing exitDescribes principal setting/milling deployment — not the entire multilateral well.
Reservoir firstArchitecture follows remaining reserves, drainage interaction and economics.

Sidetracking is an established mature-field tool because it reuses casing, slots and surface infrastructure to reach bypassed or undrained volumes. The complication appears when the host well is not depleted. A conventional sidetrack can reach the next target while permanently removing a production path that still has reservoir value.

A sidetrack can reach the next reservoir target. The development question is whether reaching it requires abandoning a production path that is still producing.

Start with remaining hydrocarbons, not the completion system

Candidate ranking should begin with remaining and bypassed hydrocarbons, geological and dynamic uncertainty, production history and incremental recoverable volume. Published mature-field workflows from PETRONAS and other operators follow this sequence: establish the reservoir opportunity first, then select the well architecture and completion response.

New target — limited valueNew target — material value
Parent bore — little remaining valueIntervention, deferment or abandonment may be preferable.Conventional sidetrack can be highly attractive.
Parent bore — material remaining valuePreserve the existing producer.Key screening case: can the new target be accessed without destroying the existing drainage path?

What TAML-3 Lite changes

The public engineering concept is simple: create a cased-hole departure while protecting the parent bore during construction, complete the additional lateral, then restore the intended production path from the original bore. This is a functional description, not a running procedure.

1 · Set and orient

Establish the casing-exit system and orientation reference for the planned departure.

2 · Construct the lateral

Create the casing exit and drill the additional reservoir contact while the parent bore is temporarily protected.

3 · Complete the lateral

Install the lower-completion arrangement selected for reservoir and operating conditions.

4 · Restore production intent

Remove the specified temporary restriction and return the required flow paths to service.

Important: “one-trip casing exit” refers to the principal setting and milling package. Lateral drilling, lower-completion installation, testing and production commissioning remain separate operations.

Cased-hole whipstock field hardware showing a production flow-path opening
TAML 3 mechanical junction gives selective access to both the mainbore and lateral.

Temporary isolation is not the same as junction integrity

A temporary barrier that protects the parent bore during lateral construction does not by itself establish permanent hydraulic isolation between branches. Mechanical junction support and long-term pressure integrity are also separate functions. TAML terminology is useful, but it should follow the functional requirements: branch support, construction protection, commingling or selectivity, intervention access and lifecycle pressure requirements.

The reservoir questions are more important than the hardware

Field evidence and modeled economics must stay separate

Reported field implementation

40 → 80 t/d

A supplied RN-Vankor reference reports the production rate increasing after the additional lateral was brought into operation while the parent bore remained productive.

This is a reported field result from one implementation. It is not a prediction that another candidate will double production.

Separate TPU economic model

+27.3% NPV

In a separate 2021–2026 economic model, the retained-parent alternative was modeled with approximately +3.4% CAPEX, +26.5% cumulative oil and +27.3% NPV versus the comparison case.

Modeled result, not a field forecast and not an Oman project forecast.

Why this matters in mature and offshore fields

The decision becomes more material when the parent bore represents not only current production but also an occupied slot, upper-hole investment, completion, artificial-lift interface, surveillance history and future intervention path. Public examples from Xijiang 24-3 and Goliat show operators using multilateral architecture when preserving existing well value or scarce offshore infrastructure materially affected the development decision.

The screening question is therefore not “Can we install a multilateral system?” It is: does the candidate contain enough value in both the existing drainage path and the new target to justify preserving both?

Public evidence boundary

This article intentionally publishes the development problem, functional architecture, evidence and limitations — not the execution recipe. Detailed BHA configuration, exact tool geometry, setting parameters, milling parameters, temporary-isolation design, contingency logic and acceptance criteria remain well-specific engineering information.

Sources and further reading

  1. SPE-176040-MS — Locating the Remaining Oil in a Mature Field in the Tertiary Baram Delta, Malaysia. Used for mature-field remaining-oil / candidate-screening context.
  2. SPE-117377-MS — Integrated Approach for Horizontal Side Track Candidate Selection in Sorochinsko-Nikolskoe Oil Field. Used for sidetrack candidate-screening context.
  3. Offshore Magazine — Xijiang 24-3 mature offshore multilateral case. Used for the parent-production preservation example.
  4. SLB — Vår Energi Goliat retrofit multilateral case. Used for the offshore slot/infrastructure preservation example.
  5. SLB Oilfield Review — The Defining Series: Multilateral Wells. Used for TAML classification context.
  6. RN-Vankor supplied field reference. Used for the reported 40 → 80 t/d field result and parent-bore-retention concept. Detailed tool dimensions and operating procedure are intentionally not reproduced here.
  7. I.V. Anikin, TPU MSc dissertation (2021), Section 4. Used for the separate modeled economic comparison. Values are presented as model results, not field forecasts.